Elevate your asset management experience with SAP Asset Management Business Process Flow AUC, streamlining operations from project definition to asset retirement.
1
Capture capital project request
2
Validate capitalization basis and scope
3
Configure investment project and AuC
4
Define cost and settlement controls
5
Approval: Capital investment
6
Release project and collect costs
7
Reconcile posted project costs
8
Execute periodic settlement to AuC
9
Assess completion and capitalization readiness
10
Resolve capitalization readiness exceptions
11
Create completed asset master data
12
Define final settlement distribution
13
Simulate and reconcile final settlement
14
Confirm depreciation and control dates
15
Approval: Capitalization
16
Post final settlement and close
Capture capital project request
Record the business purpose, ownership, expected spend, and timing for one asset-under-construction project. Use stable SAP identifiers rather than descriptive substitutes, and confirm that the request represents a distinct construction or development effort. If ownership or scope is unclear, pause the request and resolve it before configuration begins.
Validate capitalization basis and scope
Assess whether the proposed expenditure meets the organization’s capitalization policy and identify directly attributable versus non-capitalizable costs. Document the applicable accounting framework and any judgment. Costs that do not bring the asset to the location and condition needed for intended operation must not be folded into the AuC without support.
1
Eligible for capitalization
2
Partially eligible
3
Expense only
4
Policy review required
5
Insufficient evidence
Configure investment project and AuC
Create or verify the SAP investment-project WBS element, investment profile, settlement profile, and linked asset under construction. SAP recommends the WBS-based approach for new AuCs. Confirm the WBS release creates or links the intended AuC and that identifiers match the approved company code.
1
Periodic settlement
2
Event-based settlement
3
Line-item settlement
4
Summary settlement
5
Method requires review
Define cost and settlement controls
Define how capitalizable and non-capitalizable postings will be separated and where each category will settle. Use a source structure or capitalization keys when needed, and ensure all receiver percentages are complete. Record the design so a reviewer can trace posted costs to the AuC and eventual final assets.
1
Complete and balanced
2
Incomplete allocation
3
Duplicate receiver found
4
Invalid receiver found
5
Pending accounting review
Approval: Capital investment
Will be submitted for approval:
Capture capital project request
Will be submitted
Validate capitalization basis and scope
Will be submitted
Configure investment project and AuC
Will be submitted
Define cost and settlement controls
Will be submitted
Release project and collect costs
Release the approved investment project for posting and confirm procurement, time, material, and vendor transactions use the correct WBS element. Monitor the first postings for coding errors. Do not accept costs posted to convenience objects when they should be traceable to this investment measure.
Reconcile posted project costs
Reconcile the WBS ledger to invoices, goods receipts, time, and other supporting records for the settlement period. Separate capitalizable costs from expense or other receivers and investigate duplicates, unsupported items, or incorrect periods before settlement.
Execute periodic settlement to AuC
Maintain the period’s settlement rule, run settlement in simulation, resolve errors, and then post the approved settlement from the WBS element to the AuC. Confirm the capitalizable amount reaches the intended AuC and non-capitalizable amounts reach their designated receivers. Retain the SAP settlement document and error log.
1
Posted successfully
2
Simulation passed
3
Posted with warning
4
Blocked by error
5
Reversal required
Assess completion and capitalization readiness
Confirm the asset is physically complete or otherwise in the location and condition necessary to operate as management intends. Check commissioning evidence, open commitments, late invoices, defects, and remaining construction activity. Capitalization readiness is an accounting and operational conclusion, not merely a project status label.
1
Ready for capitalization
2
Not ready
3
Partially ready
4
Ready with accrual
5
Requires technical review
Resolve capitalization readiness exceptions
Resolve the specific issues preventing clean capitalization, such as open commissioning work, unrecorded obligations, uncleared down payments, missing invoices, or unsupported costs. Record the treatment for each item and obtain evidence that the remaining balance is complete and supportable before returning to final settlement.
1
Resolved
2
Accrued with support
3
Excluded from capitalization
4
Escalated for judgment
5
Still unresolved
Create completed asset master data
Create the final asset master record or records that will receive the AuC values. Validate asset class, description, cost center, location, responsible owner, useful life, depreciation key, and depreciation start data against approved policy. Use separate receivers when components have materially different useful lives.
Define final settlement distribution
Assign AuC line items or source categories to the final asset receivers and any permitted expense receivers. Validate that percentages or equivalence numbers cover the full amount without overlap and that ledger-specific rules exist where required. Preserve traceability from each receiver back to the originating costs.
1
Balanced and valid
2
Unbalanced percentage
3
Missing receiver
4
Ledger rule missing
5
Line items unassigned
Simulate and reconcile final settlement
Run final AuC settlement in simulation and reconcile the proposed credits from the AuC to debits on final assets and other approved receivers. Investigate all errors and unexpected residuals. The simulated outcome should agree to the supported capitalizable balance before approval.
1
Reconciled
2
Residual requires review
3
Receiver mismatch
4
Posting error
5
Evidence incomplete
Confirm depreciation and control dates
Confirm the available-for-use date, capitalization date, asset value date, and depreciation start date are consistent with policy and the operational evidence. Review whether late invoices or accruals require a controlled follow-up treatment. Correct date conflicts before approval because they affect recognition and depreciation.
Approval: Capitalization
Will be submitted for approval:
Assess completion and capitalization readiness
Will be submitted
Create completed asset master data
Will be submitted
Define final settlement distribution
Will be submitted
Simulate and reconcile final settlement
Will be submitted
Confirm depreciation and control dates
Will be submitted
Post final settlement and close
After approval, execute final settlement for the exact reviewed period and receivers. Read the posting result, confirm the AuC credit and final-asset debits, document any justified residual, and update the investment project status. Notify asset accounting and the operational owner that the completed asset is available for depreciation and control.
Optional cookies and similar technologies support analytics, advertising and visitor identification, and embedded content. Change or withdraw consent in Cookie settings. Cookie policy.